During construction at Eden Prairie Library this fall, contractors discovered water infiltration at the north and northeast walls, which has delayed the project schedule by about five weeks. Originally scheduled to reopen by the end of the year, the library will now open in the first quarter of 2020. 

Inside, lighting, tile and plumbing fixture installation is nearly complete. The existing skylights have been replaced, and painting has begun. Work will soon start on the barrel vault entryway ceiling.

Exterior and site work will continue this fall, including the impacted north and northeast quadrant of the building.