North Regional Library October construction update

Construction at North Regional Library was about 72% complete at the end of September.

Current work includes:  

  • Continued installation of mechanical, electrical, and plumbing fixtures
  • Continued installation of tile and carpet
  • Installation of interior doors
  • New lighting in children and teen areas
  • Completion of stormwater system for parking lot

Upcoming work in the next few weeks includes:  

  • Landscaping
  • Asphalt paving of parking lot
  • Interior glass wall installation
  • Initial start-up of mechanical systems