Augsburg Park Library building project update
Progress on the Augsburg Park Library building project is moving along. A few highlights from the first few months of work:
- New light poles, curbs and gutters in parking lot, and sidewalk going in
- Stormwater management work in progress, will provide more green space around the library
- Framing for new study rooms and a new wellness room has begun
Looking ahead:
- Asphalt will soon be laid on the reconfigured parking lot
- New walls will be framed in the interior space
- New furnishings, paint, and carpet will be installed
- Restrooms and meeting rooms will be modernized
The building will remain closed until all work is complete. The library is expected to reopen in spring 2025.
Project updates
Interested in receiving future updates on the project? Subscribe to the Augsburg Park Library updates email list or visit the Augsburg Park Library building project page.