Pierre Bottineau Library building project progressing
Progress on the Pierre Bottineau Library building project is moving along. Currently, around 50% of construction is complete. Recent work highlights include:
- Completing general demolition
- Installing new electrical pathways
- Preparing floor for new carpet tiles
- Patching and repairing existing walls
- Painting walls, ceiling, and ductwork
- Cleaning ceiling trusses
- Refinishing millwork, tables, and chairs
The building will remain closed until all work is complete. The library is expected to reopen this winter.
Interested in receiving future updates on the project? Visit the Pierre Bottineau Library building project page.